SUMMARY

New shelter installationConstruction activity on the Mill Plain corridor continued at full speed in October, with more substantial work occurring at some locations as future BRT stations continue to take shape. Overall, construction remains focused primarily on the west side of the project corridor, between Fort Vancouver Way and 97th Avenue. As work progresses, station platforms and sidewalks are largely complete at numerous locations. Shelter structures have been installed at 14 locations. On the east end of the corridor and elsewhere, fiber and utility work continues to happen concurrently with station construction.

MILESTONES

Station construction will continue on the west end of the project corridor in November. Crews will ramp up work at some new locations, including new activity at Mother Joseph Place (westbound), 97th Avenue (eastbound) and Andresen Road (eastbound). Meanwhile, work will wind down at other locations. That’s part of the phased approach to construction, so different locations see activity at different times. For fiber and utility work, activity will continue throughout the corridor.

WHAT’S NEXT?

Station construction will continue on the west end of the project corridor in October. Crews will ramp up work at some new locations, as activity at other sites winds down. That’s part of the phased approach to construction, so different locations see activity at different times. For fiber and utility work, activity will continue throughout the corridor.

Construction Phase Map

The Vine Mill Plain Construction Phases


Questions or concerns? Call or text the Mill Plain BRT construction hotline at 360-953-3330, or send an email to This email address is being protected from spambots. You need JavaScript enabled to view it..

Construction Overview

C-TRAN officially broke ground on the Mill Plain BRT project in September 2021. Construction areas will include a new transit center near 184th Avenue and Mill Plain, and 37 new station platforms along the 10-mile Mill Plain corridor.

Construction will occur in phases during the two-year work period, meaning different areas will see construction activity at different times.

Current activity

Construction is underway at multiple locations. Expect to see construction activity at these future BRT station locations along the Mill Plain corridor:

  • Fort Vancouver Way (westbound)
  • Reserve Street (eastbound)
  • V Street (westbound)
  • Grand Boulevard (eastbound)
  • Brandt Road (eastbound)
  • Brandt Road (westbound)
  • Devine Road (westbound)
  • Andresen Road (westbound)
  • Garrison Road (westbound)
  • 87th Avenue (eastbound)
  • Mother Joseph Place (westbound)
  • 97th Avenue (westbound)
  • 164th Avenue (westbound)
  • 184th Way (Mill Plain Transit Center)

The length of construction at each location will vary as crews work to complete each new station. The public should expect temporary closures of sidewalks, bus stops and traffic lanes; however, access to adjacent businesses will remain open.

Mill Plain Corridor Map (click for enlargement)

LPA Recommended Alignment